ASSIGNMENT | Change the view back to the “entry table” (1 point)

Complete the following in Microsoft Project 2013 or later:

  • Open the MS Project Assignment – Essay 5 Starting Point.mpp and make the following changes:
  • Change the view back to the “entry table” (1 point)
  • View the Tracking Gantt (1 point)
  • Display the WBS number (Outline number) on the Tracking Gantt (1 point)
  • Set the baseline. (1 point)
  • Set baseline1 (1 point)
  • Set the status date to 04/01/2020 (1 point)
  • Mark (Update)Tasks 1.1 through 4.4 as 100% complete (2 points)
  • Mark (Update) Task 5.1 to show it actually beginning on 03/20/2020 and finishing on 03/27/2020 (3 points)
  •   Notice how this impacts your entire project and pushes the final two milestones further beyond their deadlines.
  • Mark (Update) Task 5.2 to show it actually beginning on 03/28/2020 and finishing on 03/30/2020 (3 points)
  • Mark (Update) Task 5.3 as “on track” (3 points) | PLACE YOUR ORDER NOW AT writtask.com |
  • Crash your schedule by adding John Smith to help the Temporary worker complete Task 5.5 and shorten its duration to 1.5 days from 3 days (3 points) – Notice: ! with a drop-down of choices
  • Crash your schedule further by adding Joanna Edwards to Task 5.6 and shortening that down to 1 day from 2 days (3 points) – Notice: ! with a drop-down of choices
  • Crash your schedule by changing the predecessor relationship of Task 5.7 to be SS with Task 5.6 (3 points)
  • Crash your schedule further by adding Mike Whitman and Joanna Edwards to Task 5.8 and shorten its duration to 2 days (3 points)
    • Your Office Building should now be scheduled to be completed by the deadline.

BEST-ESSAY-WRITERS-ONLINE

Order Original and Plagiarism-free Papers Written from Scratch:

WE WRITE PAPERS FOR STUDENTS

Tell us about your assignment and we will find the best writer for your project.

Write My Essay For Me
PLACE YOUR ORDER